Material schedule template for interior design
A free material schedule template as a CSV file: every column explained, a filled example, and the gaps that make a schedule hard to price.
By the ArchiStudio product team
Download the template
The template is a CSV file with 24 columns and 3 example rows. It opens in Excel, Numbers and Google Sheets. Delete the example rows, then add one row for each material, finish or product in the project.
Material, finish and FF&E schedules
A material schedule lists the materials and finishes in a project with where each one goes, the product chosen, who supplies it and how much is needed. A finish schedule is the room-by-room list of surface finishes. An FF&E schedule covers furniture, fixtures and equipment. The template works for all of them: add a type column if you keep them in one list.
The columns
Every row answers the same questions, so anyone who picks up the schedule can price it and order from it.
| Column | What goes in it |
|---|---|
| Project | The project name, so rows from several projects never mix. |
| Option | The design option the row belongs to, such as Option A. Leave it blank when there is only one. |
| Room | Where the material goes. |
| Object | The element it covers, such as Feature wall or Island worktop. |
| Specified material | The material or product as you would write it on a drawing. |
| Supplier | Who you buy it from in the project's market. |
| Product code | The manufacturer's or supplier's code, so the right item arrives. |
| Notes | Finish, size, colour reference, quote reference or anything a buyer needs to know. |
| Thumbnail | A link to a product image, so the row can be recognised at a glance. |
| Product source | A link to the product page. |
| Technical document | A link to the data sheet or specification. |
| Quantity | The amount needed, as a number, or Unknown until it is measured or confirmed. |
| Unit | m², m, m³, each, set, lot, kg or litre. |
| Quantity basis | Where the quantity came from: a site measure, a drawing or the supplier's own take-off. |
| Unit price | The price of one unit, as a number, or Unknown. |
| Currency | The currency of the quote, such as AED. |
| Price date | The date of the quote or catalogue price. |
| Valid until | The date the quote expires. |
| Line estimate | Quantity times unit price, in the row's currency. Unknown when either one is unknown. |
| Lead time days | Days from order to delivery, as the supplier states them. |
| Availability | in-stock, made-to-order, unavailable or unknown. |
| Evidence | unverified, documented or supplier-confirmed. |
| Checked on | The date you last checked the supplier information. |
| Missing information | What still needs an answer before the row can be issued. |
A filled example
The three example rows show a schedule part way through. The worktop is complete: a supplier, a code, a measured quantity, a dated quote that is still valid, a lead time and the supplier's confirmation. The feature wall and the shower tray still have gaps, and their last column says which.
| Room and object | Quantity | Unit price | Line estimate | Missing information |
|---|---|---|---|---|
| Living room, feature wall | 24 m², measured from drawing A-201 | Unknown | Unknown | Supplier and code, source, price, confirmation, check date, availability, lead time |
| Kitchen, island worktop | 6.2 m², from the supplier's template | AED 950 | AED 5,890 | Nothing |
| Master bathroom, shower tray | 1 each, counted on drawing A-305 | Unknown | Unknown | Code, source, price, confirmation, availability, lead time |
Habits that keep a schedule priceable
- Write Unknown for anything not yet confirmed. A blank or a zero makes the total look complete.
- Date every price, and note when the quote expires.
- Keep one currency per row, and keep each currency in its own subtotal.
- Record the basis of every quantity.
- Link a source for every product, so anyone can check it.
- Recheck supplier information that is more than 90 days old.
Opening the file
The file is saved as UTF-8 with a byte order mark, so Excel shows m² and other symbols correctly when you open it directly. Numbers opens it as it is, and Google Sheets imports it from File, Import.
From the template to a project
These columns are the specification fields of ArchiStudio's material schedule, in the same order. In ArchiStudio, every object in an opened 3D model gets a row, missing items are flagged as you work, each currency keeps its own subtotal and you can compare finish options object by object. Its own CSV export adds the model's columns, such as the preview finish and the part ID.
Questions
What should a material schedule include?
For each row: where the material goes, the product with its supplier and code, the quantity with its unit and basis, the unit price with its currency and date, the lead time, and links to the product page and data sheet.
What is the difference between a material schedule and an FF&E schedule?
An FF&E schedule covers furniture, fixtures and equipment, the loose and fitted items in a room. A material schedule covers materials and finishes such as flooring, wall finishes and worktops. Many studios keep both in one list with a type column.
Can I use this template in Excel?
Yes. It is a CSV file saved as UTF-8 with a byte order mark, so Excel, Numbers and Google Sheets all open it.
Is the template free?
Yes. Download it, change it and use it on any project.
Why write Unknown instead of leaving a cell empty?
An empty cell or a zero can be read as a confirmed value, and it makes a total look complete. Unknown keeps the gap visible until someone fills it.